This project was a large renovation project, 110,000sf and needed to be complete in a short time period (5 months).  Prior to bidding, The Walter Fedy Partnership interviewed contractors to bid on this project, at this interview, we had to show we were capable of doing the project and had to submit a schedule to show how we could complete the project in this time period.  The schedule had to be met for classes scheduled to start in September.

The project scope included

  • demolition
  • fire rated doorways
  • complete new computer labs, kitchen facilities for the culinary program
  • new shops for electrical, welding and carpenter apprentices
  • steel studding, insulating the total exterior walls
  • spray fire proofing the underside of the 2nd floor (40,000sf)
  • some roof replacements
  • 90% of the building repainted
  • some new flooring
  • new sprinkler system thru out the building
  • replacement of hot water heating system
  • some new HVAC equipment & ductwork
  • mostly new lighting thru out
  • fire alarm upgrade thru out

We are proud to say that this project was completed on schedule with very few problems.  The owner and consultants were very happy with our performance.

 